Process Management¶
After installation of the package a new Start Event element will be available in the accordion widget of the process management. Processes can now contain a normal start point and a scheduled start point. The schedule of the start event can be configured via an interface.
Create Start Events¶
To be able to create a start event for the process management, create a process or modify an existing one.
Click on the Start Events item in the Available Process Elements widget in the left sidebar. This action will expand the Start Events options and will collapse all others doing an accordion like effect. Click on the Create New Start Event button.
In the opened popup screen fill in the Start Event Name as well as set the schedule times.
- Start event name
- A name of the scheduled based start point.
- Schedule settings
- Cron settings of the scheduled start point.
To edit an already defined start event, just click on its name in the Available Process Elements widget.
Warning
Times scheduled during daylight saving time start and daylight saving time end can have unexpected effects. At daylight saving time start it can be skipped and at daylight saving time end it can be executed twice. It is highly not recommended to schedule times when the daylight saving time starts or ends according to the server timezone.
Add Start Event to Canvas¶
To add a configured start event to the process canvas screen a free activity (not connected to other activities) is necessary. The scheduled based start event can not be connected directly to the normal start point of the process. In addition, the timer start event is not moveable. It is absolutely required to connect the scheduled based start event to a free activity. This first scheduled based activity can then be connected with a normal activity.
The initial activity of the timer start event can be any type of activity. In case of a user task activity, the process ticket is created and the process stays in this activity.
Note
Any change that is made on the process will require to re-deploy the process in order to get the change reflected in the system.